|
Bowes Construction, Inc.
2915 22nd Avenue South
Brookings, SD 57006
605.693.3557 Phone
605.693.3589 Fax
BowesConstruction.com
Directions: via Google Maps | | |
|
NEW TECHNOLOGY SPEEDS RUNWAY GRADING
A wet summer delayed reconstruction
of the airport runway until Jason Bowes decided to use the fastest available
machine-control technology to keep on schedule
When reconstruction of a Mitchell, SD, municipal airport runway
fell behind schedule because of rain in summer 2009, Bowes
Construction, Brookings, the grading subcontractor, had two
weapons at its disposal to make up for lost time: a fast-track
pavement recycling process and high-speed machine control technology.
The airport's 6,700-foot-long Runway 12-30, the longer of two
runways at the facility, was an 8-inch-thick concrete layer
with 9.5 inches of asphalt on top from the many repair projects
throughout the years. Bowes demolished and graded half of the
runway at a time lengthwise, a technique that is fairly unique
to airport construction.
First, Bowes Construction used a Wirtgen milling machine to
remove the asphalt layer on half of the pavement. A proprietary
guillotine drop hammer then broke up the concrete. Next, a
Caterpillar 330C excavator fed a Metso LT 1213S mobile track
crusher that reduced and blended the millings and broken concrete
into 3-inch pieces and stockpiled it on the other half of the
existing pavement. Bowes excavated 18 inches of soil under the
old pavement using a Caterpillar D6R dozer and widened the
subbase excavation to 134 feet to widen the runway from 100
to 124 feet.
Recycling Pavement On-Site
The recycled material was placed in the trench in uniform lifts
to form a 12 to 15-inch-thick subbase. Additional quartzite
coarse aggregate was delivered from Spencer Quarries, Spencer,
SD, and placed 18 inches deep in three 6-inch lifts.
A gyro, compass and inertial
sensor on this dozer's high-speed Topcon 3D-MC2 system take up to
100 readings a second
This project had more room than we're used to working on a
highway job. We divided the runway in half," said Jason Bowes,
vice president of Bowes Construction. “We milled the asphalt
all to one side, leveled it, then take that crusher and run
on top of it." He added that this process was possible because
Bowes Construction was allowed to recycle the old pavement on
site instead of hauling the concrete to a central facility.
Off-site recycling would have allowed full-width pavement
demolition, but that process required more time than the process
used.
However, a wet summer delayed the project. Bowes decided to
use cutting-edge machine-control technology to reduce the adverse
impact of the weather on scheduling.
The airport, which was initially constructed as a military
installation in 1945, received $6.7 million in funding under
the American Recovery and Reinvestment Act of 2009 and $450,000
in Federal Aviation Administration and state and local funding
for design and construction engineering.
Phase 2 Construction
Commercial Asphalt, Mitchell, SD, a division of Spencer Quarries,
received the contract for reconstructing the runway with a 5.5-inch
asphalt surface. Under Phase I, which started in late June 2009,
Runway 12-30 was reconstructed at the intersection of two shorter
runways. Work included asphalt milling, removing existing concrete,
excavation, sub-base and base course construction, asphalt pavement,
under drain, installing storm sewer pipes, drainage improvements,
marking, adding top soil and seeding.
In early August, Phase 2 work began on Runway 12-30 with the
construction of 12-foot-wide non-aircraft asphalt shoulders,
construction of transition pavement from the runway to one taxiway,
and the reconstruction of another taxiway to the runway safety area.
On September 1, Bowes reported that Phase 2 site work was about
two weeks behind schedule. But Jason Bowes expected the combination
of the on-site recycling process and machine-control technology to
make up one week's work and complete the project by October 1
instead of September 25 as initially scheduled.
South Dakota, the pheasant-hunting capital of the world, would
start its hunting season in November. Large numbers of hunters
were expected to fly into the airport in October, which required
use of the new runway.
GNSS on Two Dozers
To make up for lost time, Bowes Construction equipped the second
of two dozers, a Caterpillar D8T, with its Topcon 3D-MC2 Global
Navigation Satellite System (GNSS) machine-control system for
grading the subbase and base. The company had already purchased
3D-MC2 components from Laser Control Inc., Bloomington, MN, and
equipped the D6R with this system, which allowed the dozers to
move aggregate with minimal interruptions and grade with precision.
The recycled pavement goes through a mobile
track crusher and is reused to grade the new runway.
The 3D-MC2 system's components include a MC-R3 GNSS controller
that works in conjunction with an MC2 sensor that replaces a
slope sensor; a four-color, touch screen, Bluetooth-capable
GX-60 control box; and a conventional GNSS antenna mounted on
the dozer blade. The technology provides blade position readings
up to 100 times per second.
GNSS machine control is not new to Bowes Construction, although
equipping dozers with GNSS is a new practice. Starting in 2001,
the company adopted 3-D GNSS machine control and used the technology
on as many as six graders at a time.
The D6R dozer leveled off piles of quartzite aggregate while a
Caterpillar 140H grader equipped with Topcon's System 5 indicated
grading the next swath a few feet behind the D6R. Inside the dozer,
operator LaDuke Palmer viewed the dozer's position and blade
placement in real time on the GX-60 in-cab monitor and made
necessary adjustments.
Eliminating Human Errors
Although he had operated graders, scrapers and loaders without
the assistance of machine controls, Palmer had never operated a
dozer with the 3D-MC2 system on the D6R. His training on high-speed,
machine-control assisted dozer operation consisted of riding with
Jason Bowes for six hours.
"[Machine control] takes human error out of the work,” said
Palmer. "This is the beginning of the fourth week on this phase.
By the end of this week, we'll have finished the subbase and the
base. The biggest difference with this system is scheduling our
own work and continuing to move without waiting for a staker to
get in between each phase."
A design attribute of the system also boosts productivity, Bowes
added. The control box is equipped with magnets so that it can
be moved quickly and the GNSS antenna/receiver can be switched
easily to another machine. "Flexibility is big in construction
and this system has definitely moved the project forward," said
Bowes. “"Building isn't going to stop in the future."
10/19/2009-Story and Photos by Don Talend
|
|
|
NEW TECHNOLOGY SPEEDS RUNWAY GRADING
The heat was on - both
literally and figuratively - the Bowes Construction crew as they
worked to widen Highway 45 in South Dakota last August. Afternoon
high temperatures routinely pushed 100° F, and they had
just three weeks to reclaim nearly 32 km (20 miles) of road
that had a 229 mm (9") asphalt layer. Time is so tight, and
productivity so crucial, that the firm runs three Cat RM-350B
Reclaimers on the job.
"We have a simple philosophy:
Put the most productive equipment to work," says Jason Bowes,
co-owner of the firm.
Project Description
There are two components to Bowes' work on the 30 km (18.6 mile)
stretch of Highway 45. The first component, the widening of the
road from 9 to 12 m (30 to 39'), began last spring with the
laying of a dirt subgrade for the new shoulders.
The second part of the project is preparing Highway 45 for a
new asphalt surface. That work includes pulverizing existing
asphalt with three RM-350Bs. South Dakota Department of Transportation
(SDDOT) specs call for 95 percent of the pulverized material
to pass a sieve size of 25 mm (1") and 100 per cent of the material
to pass a sieve size of 38 mm (1.5"). The pulverized material
is used as subbase. It is compacted and a portion is bladed
onto the expanded shoulder subgrade. New aggregate base is added,
bladed full width and compacted. Specs call for a density of
95 per cent before the placement of the asphalt. Another firm,
which hired Bowes for the reclamation work, will handle the
paving of the newly widened road.
Reclamation
Bowes Construction specialized
in reclamation. "By concentrating in that specific area, we've
been able to learn some efficiencies," Bowes says. It was that
experience that led Jason Bowes to use three Cat RM-350Bs
simultaneously on the Highway 45 project.
"To complete this project on time, we need to finish a mile
(1,6 km) of road per day," Bowes says. "That includes everything:
reclaiming, blading, compacting, adding aggregate. Keeping that
pace for reclaiming is the most difficult part of the equation.
Our productivity really depends on how fast we can pulverize -
keeping in mind that we have pulverization specs to meet."
Maintaining the 1,6 km (1 mile) per day pace requires Bowes to
pulverize about 13 712 m2 (16,400 yd2 per
day. "We own two RM-350Bs, but realized we needed help to keep
that kind of pace," Bowes says. "We decided to rent another
RM-350B because of its productivity and our operators' familiarity
with the machine."
The operators encountered some challenges during the pulverization
process. "We had the drum sunk all the way down to 15" (381 mm)
for miles upon miles, and it did the job," says operator Brett
Westley. "Even at that depth, we move along at 12-15' (3,7-4,6 m)
per minute."
Often the drum need go only about 305 mm (12") deep. "The asphalt
typically is 9" (229 mm) deep, and we go a few inches deeper to
keep the tips cooler," says operator Mike Erickson. "At that
depth, we're able to cover about 20' (6,1 m) per minute."
But rotor depth isn't the only factor that affects production.
"We routinely encounter quartzite," says Rodney Anderson, another
reclaimer operator. "That stuff is as hard as it comes, but we're
able to get through it. That's when you're grateful for the
three speeds."
Rotor speeds on the RM-350B can be set at 115, 160 and 215 rpm.
"When we hit the harder material, we grind at 115," says Westley.
"We haven't come across anything yet that we can't grind at 115.
But if we get in some looser material, we can change the setting
and move right along. We usually pulverize at 160. It's fast
enough to be productive, but also ensures we reach our pulveration
goals. The third setting (215 rpm) is mostly for mixing."
The RM-350B also features automatic load control, which adjusts
propel speed so that the engine speed is maintained at less than
1,800 rpm. The machine always works at peak efficiency for
maximum output.
Bowes reclaimed 30 km (18.6 miles)
of Highway 45 in three weeks.
Teamwork
Bowes developed a system to maximize the use of the three RM-350Bs.
Most often, two reclaimers work together and pulverize one half
of the road. (Traffic continues to use the other half.) The
third reclaimer, meanwhile, starts pulverizing 0,8 km (0.5 miles)
ahead. The two RM-350Bs pulverize until they reach the starting
point of the third. One of the two continues to pulverize, completing
the work started by the lone reclaimer. The second RM-350B stops
pulverizing and travels down the road to catch up with the
lead reclaimer. Those two then become a team.
"It allows us to keep the road open, per SDDOT specs," Bowes said.
"It also enables us to keep the rollers and the blade busy
and complete the road in segments, which helps alleviate traffic
concerns."
In addition, the system allows Bowes to customize the rotors used
on their reclaimers.
"Two of the three machines have reclamation drums," Bowes says.
"Those drums have 188 carbide teeth and work best on asphalt. The
third reclaimer has a combi drum (with 108 teeth). We find that
it's a good strategy to have a blend. The combi still grinds well
on the asphalt but works ideally on the shoulder and first part
of the existing road, where only portions of the surface require
pulverization. Both the reclamation and combi rotors are 96" (2438
mm), which means we get consistent widths no matter which machines
are working together."
The Bowes crews know that good rotor maintenance is key to high
production. Operators check the rotor teeth about every hour.
"We usually replace 20-30 tips," Bowes says. "It takes less than
a minute per tip." When the rotor tools are in good condition,
pulverization is faster.
The Cat machines also add productivity in subtle ways, Bowes
says. "Our staggering of the machines means that the reclaimer
has to be able to move down the road when it's not pulverizing,"
Bowes says of the reclaimer, capable of traveling at speeds of
16,8 kmph (10.5 mph). "The sooner that machine starts grinding
at its new location, the more productive it's going to be."
"We have a simple philosophy:
Put the most productive equipment to work."
-Jason Bowes, co-owner, Bowes Construction
Blading And Compaction
Rolling behind the reclaimers is a Cat CP-563C Soil Compactor,
which makes two passes. "The padded compactor packs the material
right behind the reclaimer so you get some stabilization down
deep," Bowes says. The chevron pattern of the pads concentrates
full compactive effort on only two and a half pads at a time
for maximum compaction. In addition, the pad height of 127 mm
(5") helps get compaction deep in the lift, which is crucial to
Bowes. "We need the roller to bridge the old base with the
reprocessed materials," he says. "We don't do a compaction reading
after the padded roller passes, but our experience and earlier
research show that achieving that initial depth of compaction
helps us meet our final density target."
In the next step, Bowes
scarfies the surface of the reclaimed subbase, then adds water,
blades material out to the edges and creates the required slope.
Crushed stone base is transported from a portable crushing plant
about 17,7 km (11 miles) from Highway 45 and spread. Pneumatic
rollers then make two passes to get density of 95 per cent.
Reclaiming the full asphalt layer in place and converting that
layer into subbase adds substantially to the engineering value
of the structure. With a strong subbase under the base, less
virgin material is required. The savings in material, crushing
and transport are significant and make the reclamation process
attractive to public works officials. Usually, more miles of road
can be improved for the same budget during the reclamation process
compared to using total reconstruction for highway widening or
improvement.
Meeting Goals
The day draws to an end. The reclaimers have pulverized and mixed
more than a mile of asphalt. The pulverization specs have been met,
and the padded roller has laid the foundation for compaction densities.
"It's an incredible pace, no doubt about it," says Bowes. "But
it can be done. We prove that every day."
Paving News, The Roadbuiling and Maintenance Magazine from Catepillar© Paving Products, Inc., Volume 10, Issue1
| | |
| |