|
NEW TECHNOLOGY SPEEDS RUNWAY GRADING
A wet summer delayed reconstruction
of the airport runway until Jason Bowes decided to use the fastest available
machine-control technology to keep on schedule
When reconstruction of a Mitchell, SD, municipal airport runway
fell behind schedule because of rain in summer 2009, Bowes
Construction, Brookings, the grading subcontractor, had two
weapons at its disposal to make up for lost time: a fast-track
pavement recycling process and high-speed machine control technology.
The airport's 6,700-foot-long Runway 12-30, the longer of two
runways at the facility, was an 8-inch-thick concrete layer
with 9.5 inches of asphalt on top from the many repair projects
throughout the years. Bowes demolished and graded half of the
runway at a time lengthwise, a technique that is fairly unique
to airport construction.
First, Bowes Construction used a Wirtgen milling machine to
remove the asphalt layer on half of the pavement. A proprietary
guillotine drop hammer then broke up the concrete. Next, a
Caterpillar 330C excavator fed a Metso LT 1213S mobile track
crusher that reduced and blended the millings and broken concrete
into 3-inch pieces and stockpiled it on the other half of the
existing pavement. Bowes excavated 18 inches of soil under the
old pavement using a Caterpillar D6R dozer and widened the
subbase excavation to 134 feet to widen the runway from 100
to 124 feet.
Recycling Pavement On-Site
The recycled material was placed in the trench in uniform lifts
to form a 12 to 15-inch-thick subbase. Additional quartzite
coarse aggregate was delivered from Spencer Quarries, Spencer,
SD, and placed 18 inches deep in three 6-inch lifts.
A gyro, compass and inertial
sensor on this dozer's high-speed Topcon 3D-MC2 system take up to
100 readings a second
This project had more room than we're used to working on a
highway job. We divided the runway in half," said Jason Bowes,
vice president of Bowes Construction. “We milled the asphalt
all to one side, leveled it, then take that crusher and run
on top of it." He added that this process was possible because
Bowes Construction was allowed to recycle the old pavement on
site instead of hauling the concrete to a central facility.
Off-site recycling would have allowed full-width pavement
demolition, but that process required more time than the process
used.
However, a wet summer delayed the project. Bowes decided to
use cutting-edge machine-control technology to reduce the adverse
impact of the weather on scheduling.
The airport, which was initially constructed as a military
installation in 1945, received $6.7 million in funding under
the American Recovery and Reinvestment Act of 2009 and $450,000
in Federal Aviation Administration and state and local funding
for design and construction engineering.
Phase 2 Construction
Commercial Asphalt, Mitchell, SD, a division of Spencer Quarries,
received the contract for reconstructing the runway with a 5.5-inch
asphalt surface. Under Phase I, which started in late June 2009,
Runway 12-30 was reconstructed at the intersection of two shorter
runways. Work included asphalt milling, removing existing concrete,
excavation, sub-base and base course construction, asphalt pavement,
under drain, installing storm sewer pipes, drainage improvements,
marking, adding top soil and seeding.
In early August, Phase 2 work began on Runway 12-30 with the
construction of 12-foot-wide non-aircraft asphalt shoulders,
construction of transition pavement from the runway to one taxiway,
and the reconstruction of another taxiway to the runway safety area.
On September 1, Bowes reported that Phase 2 site work was about
two weeks behind schedule. But Jason Bowes expected the combination
of the on-site recycling process and machine-control technology to
make up one week's work and complete the project by October 1
instead of September 25 as initially scheduled.
South Dakota, the pheasant-hunting capital of the world, would
start its hunting season in November. Large numbers of hunters
were expected to fly into the airport in October, which required
use of the new runway.
GNSS on Two Dozers
To make up for lost time, Bowes Construction equipped the second
of two dozers, a Caterpillar D8T, with its Topcon 3D-MC2 Global
Navigation Satellite System (GNSS) machine-control system for
grading the subbase and base. The company had already purchased
3D-MC2 components from Laser Control Inc., Bloomington, MN, and
equipped the D6R with this system, which allowed the dozers to
move aggregate with minimal interruptions and grade with precision.
The recycled pavement goes through a mobile
track crusher and is reused to grade the new runway.
The 3D-MC2 system's components include a MC-R3 GNSS controller
that works in conjunction with an MC2 sensor that replaces a
slope sensor; a four-color, touch screen, Bluetooth-capable
GX-60 control box; and a conventional GNSS antenna mounted on
the dozer blade. The technology provides blade position readings
up to 100 times per second.
GNSS machine control is not new to Bowes Construction, although
equipping dozers with GNSS is a new practice. Starting in 2001,
the company adopted 3-D GNSS machine control and used the technology
on as many as six graders at a time.
The D6R dozer leveled off piles of quartzite aggregate while a
Caterpillar 140H grader equipped with Topcon's System 5 indicated
grading the next swath a few feet behind the D6R. Inside the dozer,
operator LaDuke Palmer viewed the dozer's position and blade
placement in real time on the GX-60 in-cab monitor and made
necessary adjustments.
Eliminating Human Errors
Although he had operated graders, scrapers and loaders without
the assistance of machine controls, Palmer had never operated a
dozer with the 3D-MC2 system on the D6R. His training on high-speed,
machine-control assisted dozer operation consisted of riding with
Jason Bowes for six hours.
"[Machine control] takes human error out of the work,” said
Palmer. "This is the beginning of the fourth week on this phase.
By the end of this week, we'll have finished the subbase and the
base. The biggest difference with this system is scheduling our
own work and continuing to move without waiting for a staker to
get in between each phase."
A design attribute of the system also boosts productivity, Bowes
added. The control box is equipped with magnets so that it can
be moved quickly and the GNSS antenna/receiver can be switched
easily to another machine. "Flexibility is big in construction
and this system has definitely moved the project forward," said
Bowes. “"Building isn't going to stop in the future."
10/19/2009-Story and Photos by Don Talend
|